SPR Buildtech LtdLtd
20 / 6 , Nuchem Compound Mathura Road, Faridabad


 
Project Elevation Imperial Estate, Faridabad Top
 
Floor Plan   Top
 

3 Bed Room with Utility

3 Bed Room without Utility
Project Highlights   Top
 
Waiting Lounge
Reception (at each Tower) Wi-Fi Facility Dish Connection
Free Intercom Services Swimming Pool Multi Purpose Hall
Television Lounge Business Centre Basket Ball Court
Gym & Health Club Kids Theme Park Kids Bus Shelters
Creche Kids Play Area Reception
Spa Jacuzzi Sauna
Steam Rooms Designer Fittings Italian Marble Floors
Decorated False Ceilings Modern Accessories Bathrooms with Porcelain Tiles
CCTV Manned Security Intercom Connectivity
Fire Fighting System Earthquake Resistant  
Meditation Hall Yoga Centre Kids Play Area
Exclusive Space for Parties Sitting Areas Centre Plaza & Amphitheater
Jogging/Walking Tracks Ornamental Plants Fountains & Water Bodies
  Badminton Court  
 

PRICE LIST

  Top

For very limited stock

S. No. Size in sq. feet Accommodation Price Per Sq. Feet Inaugural Disc. Price Per Sq. Feet BSP Booking Amount
1. 1850 3 BR +3T(DELUXE) 2100 150 1950 3607500 360750
2. 1881 3 BR +3T(DELUXE) 2100 150 1950 3667950 366795

Plan A - Down Payment Plan

At the time of Booking

15% of BSP

Within 45 days of Booking

8% Discount on BSP + 72% of BSP + 50% 
ADDITIONAL CHARGES + 100% PLC + EDC + IDC

At the time of Possession

5% of BSP + 50% additional charges
Note: Discount rate of 8 % can be reduced / withdrawn by the Company from time to time.Company reserves the right to withdraw inaugural Discount at any time.

Plan B - Construction Link Plan

At the time of Booking

10% of BSP

Within 45 days of Booking

10% of BSP

Within 75 days of Booking

10% of BSP + 25% EDC & IDC

On start of Excavation

10% of BSP + 75% EDC & IDC

On Completion of Foundation

7.5% of BSP + 25% PLC

On Completion of Ground floor roof slab casting

7.5% of BSP + 25% PLC

On Completion of 2nd floor roof slab casting

7.5% of BSP + 25% PLC

On Completion of 5th floor roof slab casting

10% of BSP + 25% PLC

On Completion of 7th floor roof slab casting

7.5% of BSP

On Completion of 9th floor roof slab casting

5% of BSP

On Completion of 12th floor roof slab casting

5% of BSP

On Completion of 15th floor

5% of BSP + 50% additional charges

At the time of Possession

5% of BSP + 50% additional charges


PREFERENTIAL - LOCATION CHARGES (PLC) (Optional)

Green or Club Facing

Rs. 100 per sq.ft

Ground Floor

5% of BSP

1st floor

4% of BSP

2nd floor

3% of BSP

ADDITIONAL CHARGES (One time Payment) (Mandatory)

Car Parking

Open Rs.100000/-
Covered Rs.175000/-

Power Back up 
(Minimum 2 KVA / Maximum 5 KVA)

Rs. 25000 per KVA

Club Membership

Rs.50000

Interest free maintenance security

Rs. 50 per sq.ft

EEC & FFC

Rs.40 per sq.ft

E.D.C & I.D.C Rs.141 per sq.ft
Note: -
 
  1. Prices are firm and esclation free from the respective dates of booking. Prices indicated above are subject to revision at the discretion of the Company. Prices ruling on the date of Booking shall be applicable.

  2. The above prices are Exclusive of External Development Charges (EDC) & Infrastructure Development charges(IDC). At present these charges are (Rs.125/- + 16 ) Rs.141/- per sq.ft. In case of any upward revision thereof or any other charges by any Govt.Agencies in future, the same will be recovered on pro -rata basis.

  3. Other charges are indicated in the Buyer Agreement shall be payable additionally.

  4. The Payment due for construction link Plan on the basis of present stage of Construction shall be paid within 30 days of booking and the balances shall be paid as per construction done at site.

  5. Project will be completed within 36 months from the allotment date with penalty clause.

  6. Registration Stamp Duty and other charges as applicable would be payable by the allottee at the time of execution of sale deed, which shall be extra.

  7. Any additional facility, if provided will be charged extra.

  8. The above area are super -built up area which includes covered plus proportionate share of common area such as stair case, passage, community space, lift facilities etc.

  9. All building plans, layout, specifications etc. are tentative and subject to variation and modification as decided by the Company or competent authority sanctioning such plans.

  10. All Cheques/ DD should be made in favour of "SPR Buildtech Ltd" payble at Faridabad/Delhi

 

Road Map

  Top